We are coming to the end of the structural work of our renovation project. A new staircase carcass has been installed and now meets current building regulations, display stands in both the ground floor and first floor showrooms have been installed and room sets are starting to be laid out.
New unfinished staircase leading up to the first floor showroom, to be covered with solid oak boards at the end of the project.
All first fix electrics and plaster boarding has been completed in both the ground and first floor showrooms and offices and is now ready for the plasterers to come back to complete these rooms.
Newly plaster boarded ceiling and the start of the room set construction.
Once the plastering and second fix electrics has been completed on the first floor we are ready to open up the double height section of the showroom and fit the three large scale Chandeliers, this will reveal the true scale of the renovation and bring the whole design to life.
More updates to follow in the coming days.